A new home handover is not just the end of a construction project — it is the beginning of your warranty obligations and the point at which your customer’s experience of your business is either cemented as positive or starts to go wrong. Builders who invest in thorough handover documentation have fewer disputes, faster DLP resolution, and significantly better referral rates.
Why documentation protects builders
Without thorough documentation at handover, disputes become a question of “they said, we said.” With documentation:
- You have dated photographs showing the condition of the home at handover — so any claim for damage that occurred after occupation can be assessed against an objective baseline
- You have a signed practical completion certificate that records the homeowner’s agreement to accept the home and lists any agreed outstanding items
- You have a record of what was agreed to be defects vs what was assessed and rejected
- You have evidence of the quality of work at the point of handover, which protects against later claims that are exaggerated or fabricated
The cost of documentation — time for photography, organising the certificate, briefing the customer — is trivial compared to the cost of a disputed defect claim that goes to QCAT, NCAT, or VCAT.
Before the practical completion inspection (PCI)
Before the PCI, the site supervisor or project manager should:
Conduct your own walkthrough Before the customer’s PCI, walk through the entire home yourself and identify any outstanding items. Resolve what you can before the customer sees it — it is far better to fix something proactively than have it raised as a defect on the completion certificate.
Photograph every room Take a complete photographic record of the finished home: every room from multiple angles, all wet areas (bathrooms, laundry, ensuite), all external surfaces, roof (if safely accessible), garage, all tiling, all painted surfaces, all joinery, and all fixtures. These photos should be dated and retained.
Prepare the completion documentation package Have ready for handover:
- Practical completion certificate (signed by you as builder, ready for customer signature)
- Defect and omissions list (blank, for recording items at the PCI)
- Warranty documents (including home warranty insurance certificate)
- Appliance manuals and warranty cards for all installed appliances
- Trade certificates (plumbing compliance certificate, electrical compliance certificate, waterproofing compliance certificate)
- Any council or certifier documentation (occupation certificate, compliance certificate)
- Contact information for the DLP process
During the practical completion inspection (PCI)
Approach the PCI as a collaborative process. The homeowner has the right to commission an independent building inspector — accommodate this and do not treat it as adversarial. A confident, professional approach to an independent inspection is a mark of quality work, not a threat.
Walk the entire home systematically Cover every room, every surface, every fixture. Do not rush. A thorough PCI typically takes two to four hours for a standard residential build.
Record everything As defects are raised, record them on the defect and omissions list:
- Location (room, surface, element)
- Description of the issue
- Your response: accept as defect, dispute, or note for investigation
- Scheduled rectification date (for accepted defects)
Photograph disputed items Where you dispute a claimed defect, photograph the item at the time of the PCI so you have a contemporaneous record of its condition. This protects you if the homeowner later claims the condition has worsened.
Be clear about what you accept and what you do not Do not accept defects vaguely to get past the moment and address them later. If you accept a defect, confirm when it will be rectified. If you dispute a claim, explain clearly why (reference the building standard if possible) and put that in writing.
The practical completion certificate
The practical completion certificate is a critical document. It records:
- The date of practical completion
- The parties
- Any defects and omissions agreed to be outstanding
- The homeowner’s agreement to accept the home on the stated basis
Ensure the certificate:
- Is signed by both parties
- Lists any agreed outstanding items specifically (not “various items to be rectified” — list each one)
- References the fact that the defects liability period commences from this date
- Is retained in your project records
If a homeowner refuses to sign the completion certificate while simultaneously claiming you should make good on items they have agreed are complete, seek legal advice. The certificate protects both parties — a homeowner who refuses to sign without clear written grounds is creating a contract dispute.
The handover briefing
At handover, brief your customer on:
- The DLP — when it ends, how to notify defects, and who to contact
- The warranty periods — the statutory warranty periods for structural vs non-structural defects
- How to submit a defect notification — by email to a specific address, in writing, with photos
- What is and is not covered — normal wear and tear, items the homeowner modifies, and damage after occupation are not your responsibility
A written summary of this briefing — handed over with the documentation package — reduces confusion and disputes during the DLP.
Post-handover: the first 30 days
The first 30 days after handover is when most minor issues become apparent. Be accessible. Respond to notifications promptly. Early professional handling of minor issues prevents them from becoming major relationship problems.
Set up a simple DLP register: customer name, date of notification, description, assessment, scheduled rectification, and completion date. Reviewing this register at a weekly meeting keeps the DLP under control.
Key Takeaways
- Comprehensive photography before the PCI creates a baseline record that protects you from claims for post-handover damage; photograph every room, surface, and fixture from multiple angles with dates
- The practical completion certificate must be signed by both parties and specifically list any agreed outstanding defects — vague language invites disputes
- Have your full documentation package ready at handover: warranty certificates, appliance manuals, trade compliance certificates, and occupation certificate
- Brief the customer clearly on the DLP process at handover — who to contact, how to submit notifications, and what is and is not covered
- Manage the DLP with a systematic tracking register; respond within five business days of each notification and communicate timelines proactively
- Recommending Checka to customers changes how defects are communicated — structured reports replace vague complaints, making the DLP easier to manage for everyone
Free to download
Stop losing track of defects.
Checka helps you capture issues, stay organised, and arrive at handover with a complete record of your build.